page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49 page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
47
in the example. Then head loss in 1m length of canal for each
case should be calculated. The corresponding energy loss (or
power loss in most cases of micro-hydro) due to the head loss
over a year should be calculated. Then, the cost corresponding
to the energy loss should be calculated and the sum of energy
or power loss cost discounted over the plant’s economic life
(generally 15 years) for a discount rate (generally 10 %) is
determined. Note that the discount rate is the opportunity
cost of investment in the prevailing market and should be
greater than or at least equal to the prevailing lending rates
for infrastructure projects by the commercial banks of the
country. The longitudinal canal slope corresponding to the
minimum of sum of canal cost and energy loss cost as shown
in Figure 4.6 will be the optimum canal slope which
determines the canal size (depth and width).
Figure 4.6 Canal optimization
Canal optimization example
Design flow which was fixed earlier based on hydrology and
electricity demand , Q= 300 l/s =0.3 m3/s
Decide canal shape and lining method (according to site
condition): Rectangular, stone masonry (1:4) with base slab
and side walls, t=300 mm=0.3 m thick and free board,
F= 300 mm=0.3 m
Manning’s constant from table 4.1, n= 0.02
Assume an appropriate longitudinal slope of canal, S=1/500
(1 in 500) in this case
Select a width to depth ratio, B/D=r=2, (generally 2 is
optimum if site condition allows and should be lowered if
width is a constraint)
D
=
⎣⎢
Q
×n×
5
r3
(r +
1
×S
2)
2
2
3
3
8
⎥⎦
=
0.3
×
0.02
×
(2
+
2)
2
3
⎣⎢
51
2 3 × (1/ 500) 2
3
8
⎦⎥
=0.43m
Note that the above equation is derived from Manning’s
equation. Sizing and quantity calculations can be done
similar to this procedure for unlined or trapezoidal canal using
Manning’s equation.
Considering length of canal, L=1 m
Base slab:
B=r*D=2*0.43=0.86 m
Width, W=B+2*t=0.86+2*0.3=1.46 m
Quantity, Vb=W*t*L=1.46*0.3*1=0.44 m3
Walls:
Wall height, H=D+F=0.43+0.3=0.73 m
Quantity, Vw=2*t*H*L=2*0.3*0.73*1=0.44 m3
Total quantity, Vt=Vb+Vw=0.44+0.44=0.88 m3
Stone masonry rate, say Rm=4000 Rs/m3
Cost of canal, Cc=Vt*Rm=0.88*4000=Rs 3200
Head loss, HL=L*S=1*1/500=0.002 m
Overall efficiency, e=0.5, generally for micro-hydro
Power loss based on the power equation discussed in Chapter
1, PL=QgHLe=0.5*9.81*0.3*0.002=0.00294 kW=2.94 W
Power tariff, Rp =Rs 1.0 per kW/month (say)=NRs 12 per kW/
year
Energy/Power loss cost per annum, C=PL*Rp=2.94*12=Rs
35.28
If the tariff is based on energy i.e., Per kilo Watt Per hour
basis, then energy loss (EL, kWh) all around the year should
be calculated considering the plant factor (P) (generally 0.2 to
0.5 for micro hydro). Then energy loss should be multiplied
by energy rate (Re, Rs/kWh) to determine cost of loss over a
year (C).Thus, EL=8760*P*PLC=EL*Re
Assuming the following parameters for the financial analysis:
Plant’s economic life N=15 years
Discount rate, i=10%
Discount factor of annuity
DFA
=
(1 + i)N i
i × (1 + i)N
=
(1 + 10%)15 10%
10% × (1 + 10%)15
=9.76
Therefore power loss cost, Ce=C*DFA=35.28*9.76= Rs.
344.33
Now, total cost, Ct=Cc+Ce=3200+344.33=Rs. 3544.33
Similarly costs for various canal slopes should be calculated
and plotted to find the minimum total cost (as shown in
Figure 4.6). The corresponding canal longitudinal slope for
the minimum total cost will be the optimum slope.
4.3.2 MANNING’S EQUATION
The design of a headrace canal is based on Manning's equation.
Manning's equations for flow and velocity are as follows:
Q
=
AR2/3
n
S
V=
R2/3 S
n
where:
Q is the flow in the canal in m3/s
V is velocity in the canal in m/s